The below described scope of work is for Train 1 only. Train 2 scope of work currently is not fully clear. Once SOLAR packages arrive from Houston and cleanliness inspections have been completed, Work-packs shall be generated by COMPANY and will be submitted to Subcontractor for executions using the same unit rates as defined for Train.
A Boroscope exercise was carried out on skids delivered from Houston, process skids and pipe rack modules. The findings, minor debris and scaling, deem it necessary to perform air blowing as per the following work packs:
Air Blowing will be carried out as per the referred procedure “FCP Gas Train 1 Cleanliness” (Doc. no. GAS1-GP1-SIP-MP-6025-0001). Subcontractor shall supply all manpower, consumables, tools, plant and equipment to execute air blowing works.
In addition to the air blowing it has been decided that chemical cleaning should be carried out on the following systems as per the referred marked-up P&IDs
Copyright © 2025 Sumarcade LLC - All Rights Reserved.